CASE STUDY

Maximum Safety

THE CHALLENGE

CB&I (Shaw) hired CSM for the cladding scope of a new coal powered power plant. Numerous trades had to work together to complete this project with an excellent safety record. 

The SCOPE

215,000 SF

of insulated metal siding

$8.1M

contract amount

48,000 SF

of single skin metal siding

The outcome

CB&I performed several safety audits per day, which our crew passed with flying colors. The project won numerous awards, including ENR Safety Project of the Year, Power Magazine Coal Project of the Year. After completing this project, CSM added to its record of over 14 years without a lost time incident.